Week 6: Installation of the new ECO slates is complete. The new roof finish has achieved the desired sharp & clean look. AthyECOSlate’s www.athyecoslate.com Click here to read more about this project.
Week 5: Now that the majority of the mechanical and electrical first fix is complete, the spray foam insulation can be installed to the full extent of the timber frame structure. Once the installation of the spray foam insulation is complete, an airtight or...
Week 4: The new cut roof structure is sheeted with marine ply and the new ‘FAKRO’ breather membrane is installed above this. Batons and counter batons are then fixed in place and the new recycled roof slates are laid. Internally, the new timber stud walls...
Week 3: At the beginning of a week of good forecast weather, the existing roof truss’s are removed and preparation is made for the new cut roof to be constructed. Click here to read more about this project.
Week 2: The original roof tiles have been stripped back and temporary waterproof sheeting is positioned to protect the dwelling. The house has been stripped back to expose the timber frame structure internally. Due to the fact that none of the internal stud walls...