Week 15: The carpets have been laid in all of the room at first floor as the contract works near completion. The house is now ready for the client to move back in! Click here to read more about this project.
Week 14 (cont.): The Solar Hot Water system has been commissioned. The solar panels have been located on the optimum south facing roof surface to the rear so as to achieve maximum efficiency. Click here to read more about this project....
Week 14: The internal doors and ironmongery have been fitted. All bathrooms have been tiled and all sanitary ware has been second fixed. With the flooring down and the walls painted, the new bright spacious double height entrance space is nearing completion with...
Week 13: All of the internal walls and ceilings have now been painted and the electrical and mechanical second fix is almost complete. This timber flooring has been laid internally and the hardwood ‘balau’ decking boards are also currently being fitted....
Week 12: The new kitchen units have been fitted meaning that the new appliances can be fitted and all associated work can now be completed. The new walnut timber flooring will be laid throughout the entire ground floor at the end of this week. Click here to read more...