WEEK 9: All of the blockwork walls of the new extension to the side and rear of the existing house are now complete. Externally, all garden walls to the rear are being rendered with sand and cement. The walls of the original house and extension and being prepared for...
WEEK 8: The construction of the blockwork walls at 1st floor and the two single storey roofs are nearing completion. To the front of the house, the new front door ope has been constructed and the new entrance hall has started to take shape. The existing windows which...
WEEK 7: The construction of the blockwork walls to the ground floor extension have been completed. The 1st floor joists have been put in place and the walls of the 1st floor extension are under construction. Internally, the new open-plan kitchen / living / dining...
WEEK 5: The majority of the ground floor slab has been constructed. Having been fabricated off site, the independent steel frame structure has now also been fixed in place. The 215mm block work wall has also been constructed to the inside face of the double layer of...
RIAI PUBLIC CHOICE AWARD 2011 The RIAI Public Choice Award gives the public the opportunity to vote for their favourite building in 2011 from a diverse shortlist of 38 projects – ranging from inspiring home extensions to pastoral centres and new urban landmarks. This...