WEEK 10: Installation of the external insulation system has commenced. 100mm of a carbon enhanced grey expanded polystyrene insulation will be bonded to the full extent of the external walls of the original and new sections of the house, effectively wrapping the house...
WEEK 9: All of the blockwork walls of the new extension to the side and rear of the existing house are now complete. Externally, all garden walls to the rear are being rendered with sand and cement. The walls of the original house and extension and being prepared for...
WEEK 8: The construction of the blockwork walls at 1st floor and the two single storey roofs are nearing completion. To the front of the house, the new front door ope has been constructed and the new entrance hall has started to take shape. The existing windows which...